WSJF: Weighted Shortest Job First

SAFe®'s model for economic prioritization — doing the jobs with the highest cost of delay relative to their size first.

🚆 SAFe® · 2 min read · By Nasir A., SAFe® SPC

⚡ Key takeaways

  • WSJF = Cost of Delay ÷ Job Size.
  • Cost of Delay = user-business value + time criticality + risk reduction/opportunity enablement.
  • Score relatively, one column at a time, using a modified Fibonacci scale.

Weighted Shortest Job First (WSJF) prioritizes work to deliver the best economic outcome. The idea: if two jobs have the same value, do the smaller one first; if they're the same size, do the more valuable one first.

WSJF = Cost of Delay ÷ Job Size
Cost of Delay = User-Business Value + Time Criticality + Risk Reduction / Opportunity Enablement

How to score

  1. 1List the features (or epics) to compare.
  2. 2Score one column at a time across all items, using a modified Fibonacci scale (1, 2, 3, 5, 8, 13, 20).
  3. 3Give the smallest item in each column a 1 and score the others relative to it.
  4. 4Calculate WSJF and sort from highest to lowest.
FeatureValueTime crit.RR/OECost of DelayJob sizeWSJF
A8531682.0
B5811434.7
C133521131.6

Here Feature B goes first: it isn't the most valuable, but its high time criticality and small size give the best return.

🧠 Test yourself

Two features have the same Cost of Delay. Which should go first under WSJF?