Agile Release Train (ART) and PI Planning

How SAFe® aligns teams into Agile Release Trains that plan and deliver together every Planning Interval.

🚆 SAFe® · 2 min read · By Nasir A., SAFe® SPC

⚡ Key takeaways

  • An ART is a long-lived team of agile teams delivering a shared solution.
  • A Planning Interval is typically 8–12 weeks, often four iterations plus an IP iteration.
  • PI Planning is a two-day event where the whole ART aligns and commits.

The Agile Release Train

An Agile Release Train (ART) is a long-lived team of agile teams — typically 50–125 people — that, together with stakeholders, incrementally develops, delivers, and operates one or more solutions.

The Planning Interval (PI)

A Planning Interval (called a Program Increment before SAFe® 6.0) is a fixed timebox, usually 8–12 weeks. A common pattern is four development iterations followed by one Innovation and Planning (IP) iteration.

PI Planning

PI Planning is a face-to-face (or virtual) event, typically two days, where everyone on the ART plans the next PI together.

  • Day 1: business context and vision, architecture and UX guidance, then team breakouts to draft plans; a management review resolves issues.
  • Day 2: teams adjust plans, finalize PI objectives (with business value assigned by Business Owners), review risks, and take a confidence vote.
  • Outputs: committed team and ART PI objectives, and an ART planning board showing features, dependencies, and milestones.

Managing risks: ROAM

Risks raised in PI Planning are ROAMed: Resolved, Owned, Accepted, or Mitigated.

🧠 Test yourself

In ROAM, what does the "O" stand for?