⚡ Key takeaways
- Lead time is what the customer experiences; cycle time is how long the team actively works.
- Throughput counts finished items per period — simple and powerful for forecasting.
- Little's Law: average lead time = average WIP ÷ average throughput.
| Metric | What it measures |
|---|---|
| Lead time | From request (item created) to delivery — what the customer feels. |
| Cycle time | From when work starts to when it's done. |
| Throughput | Number of items finished per period (e.g., per week). |
| Work in progress (WIP) | Number of items started but not yet finished. |
| Flow efficiency | Active work time ÷ total lead time — how much time items spend waiting. |
Little's Law
Average lead time = Average WIP ÷ Average throughput
Example: a team with 20 items in progress that finishes 10 items per week has an average lead time of about 2 weeks. Cut WIP to 10 and — with the same throughput — lead time drops to about 1 week.
SAFe® flow metrics
SAFe® measures flow with six metrics: flow distribution, flow velocity, flow time, flow load, flow efficiency, and flow predictability.
🧠 Test yourself
A team has 30 items in progress and finishes 10 per week. What's the average lead time?