⚡ Key takeaways
- The Definition of Done applies to every Increment; acceptance criteria are specific to one story.
- Work isn't Done until it meets both.
- A Definition of Ready is optional and can help — but shouldn't become a gate.
| Definition of Done (DoD) | Acceptance criteria | |
|---|---|---|
| Applies to | Every backlog item and the Increment | One specific story |
| Owned by | The Scrum Team (or the organization's standard) | The Product Owner, with the team |
| Answers | "Is this built to our quality standard?" | "Does this do what the user needs?" |
| Example | Code reviewed, tests passing, documented, deployed to staging | "A confirmation email is sent within one minute of payment" |
A story is only Done when it meets its acceptance criteria and the Definition of Done. If it doesn't meet the DoD, it can't be released or shown as complete at the Sprint Review.
What about a Definition of Ready?
Some teams use a Definition of Ready — a checklist that a story is clear, sized, and small enough before it enters a Sprint. It's not part of the Scrum Guide. Use it as a helpful guideline, not a rigid gate that slows collaboration.
🧠 Test yourself
Which applies to EVERY backlog item?