Burndown and burnup charts

How to read burndown and burnup charts — and why a burnup often tells a more honest story.

🛠️ Jira & tools · 2 min read · By Nasir A., SAFe® SPC

⚡ Key takeaways

  • A burndown shows remaining work; a burnup shows completed work against total scope.
  • Burnups make scope changes visible, which burndowns can hide.
  • Use charts to start conversations, not to judge teams.

Burndown chart

A burndown chart plots remaining work (points, items, or hours) against time. An "ideal" line shows a steady pace from the start to zero at the end of the sprint.

  • Above the ideal line — behind; work may not finish.
  • Below the line — ahead of pace.
  • Flat for days, then a cliff — work isn't being finished in small pieces, or the board isn't being updated.

Burnup chart

A burnup chart plots two lines: work completed rising over time, and total scope. The gap between them is the remaining work.

The advantage: when scope is added, a burndown can look like the team slowed down, but a burnup clearly shows the scope line jumping up. That makes burnups great for releases and product roadmaps.

🧠 Test yourself

Which chart makes scope changes most visible?

Next upWhat is Agile?